A Notice of Commencement is a Florida document recorded before construction begins that identifies the owner, contractor, lender and property for lien purposes.
Florida’s construction lien law gives contractors, subs and suppliers the right to lien a property they improved but were not paid for. The Notice of Commencement is the document that starts that clock. Signed by the owner and recorded in the county’s official records, it identifies the property, the owner, the contractor, the surety if any, and the lender. It is generally required before work begins on improvements above a set dollar threshold, with a separate threshold for HVAC repair or replacement.
Building departments in Florida generally require a recorded Notice of Commencement before the first inspection on a permitted job. A certified copy is typically posted at the job site. The notice expires one year after recording unless a different date is specified, so long rehabs may need it extended or refiled. Once it is recorded, subcontractors and suppliers can serve notices to owner, and the owner must manage payments carefully to avoid paying twice for the same work.
Timing matters to lenders. Construction liens can relate back to the recording of the Notice of Commencement, so a lender wants its mortgage recorded first. On a purchase financed through Think Private Lending for a Think Off Market listing, that means the loan closes and records, then the notice is recorded for the rehab. If you record a notice before closing, call the lender first. It can affect lien priority and delay the deal.
In practice: close, record the notice, pull permits, start work. Collect lien waivers or releases from your contractor and major subs before or with each payment, and keep them with your draw records. When the job is done, the owner can record a notice of termination. It is paperwork, but it is the paperwork that keeps a $3,000 unpaid supplier from becoming a lien on the house you are trying to sell.