Rehab · 6 min read

Hiring and running the crew that does the work

The contractor you choose decides whether a rehab finishes on budget, on schedule and to code. In Florida, start with a valid state license and real insurance, compare bids against one written scope, tie payments to verified work, and collect lien releases with every payment.

Licensed is the starting line

Florida licenses contractors through the Department of Business and Professional Regulation, and you can look up any license online by name or license number in a couple of minutes. Certified contractors hold a state license that is valid statewide. Registered contractors hold a license tied to specific local jurisdictions. Trades such as electrical, plumbing, mechanical and roofing have their own license categories. Confirm the license is active and that it covers the work you are hiring for.

Unlicensed contracting for work that requires a license is illegal in Florida, and the practical risks to you are large: permits that cannot be pulled, work that fails inspection, no recourse when things go wrong, and lenders and insurers who will not accept the job. A cheaper bid from an unlicensed crew is rarely cheaper by the end. Check the license yourself rather than trusting a number printed on a truck or a business card, and look at the complaint and discipline history while you are on the same page.

Insurance certificates you should hold

Ask every contractor for a certificate of insurance naming your LLC as certificate holder, and confirm the coverage directly with the insurance agent listed on the certificate. A certificate photocopied from last year is worth nothing if the policy has lapsed. Keep current certificates in your project folder for every contractor and every sub who comes onto the property.

  • General liability coverage for property damage and injuries caused by the work.
  • Workers’ compensation coverage or a valid state exemption certificate for the business owner.
  • Auto coverage for vehicles used on the job.
  • Your LLC listed as certificate holder, with the policy dates covering your project.

Getting bids you can compare

Bids are only comparable when every contractor is pricing the same job. Write the scope of work first, room by room and system by system, with materials and quantities, and send that same document to each bidder. Ask them to price it line by line and to call out anything they would add, remove or change. Then you are comparing prices, not guessing which contractor left out the drywall.

Expect bids to vary. The lowest bid is not automatically the worst, and the highest is not automatically the best. Look for missing items, unrealistic schedules and allowances that are too low for the finish you want. Ask each contractor how they handle surprises. A contractor who answers that clearly is usually one who has done this kind of house before. Ask for two or three recent references on similar Florida rehabs, and call them.

What belongs in the contract

A written contract protects you and the contractor equally, and for a financed rehab it also lines up the work with the lender’s draw process. It should reference the scope of work, state the total price, list a payment schedule tied to completed milestones, set a start date and an expected completion date, describe how change orders are approved and priced, and spell out warranty terms.

Keep deposits reasonable and tied to a real purpose, such as ordering windows or roofing materials. Avoid large upfront payments that are not tied to work in place. Require that change orders be written and signed before the extra work begins, including the cost and any effect on the schedule. Verbal change orders are the root of most contractor disputes.

Draws and how payments move

On a rehab funded through Think Private Lending, the loan covers up to 90% of the purchase price plus 100% of the rehab budget, with the rehab money paid in draws as work is completed and verified, inside the lender’s limit against ARV. That structure works best when your contractor’s payment schedule mirrors the draw schedule, so each payment lines up with a stage of work that can be checked.

A simple pattern is to group the scope into phases: demolition and dry-in, rough systems and inspections, close-up, kitchens and baths, finishes and punch list. When a phase is done, the contractor documents it with photos and passed inspections, you request the draw, and the lender verifies and releases funds. Explain this to your contractor before you sign. Contractors who understand the draw process plan their cash flow around it.

Lien releases with every payment

Before each payment, collect a lien release from the general contractor for the work being paid, and from any sub or supplier who has served you a Notice to Owner. Releases tie each payment to a matching waiver of lien rights for that amount. Without them, a sub the contractor did not pay can file a lien against your property even though you paid in full.

At final payment, collect the contractor’s final payment affidavit and final releases from everyone who served notice. That package is what your title company and your buyer’s title company will want to see. Keeping it organized from the first draw means you will never scramble for it at the end.

Building a schedule that holds

A realistic schedule follows the order of the work and leaves room for inspections and materials. Roofing and openings usually come first to dry the house in. Rough electrical, plumbing and mechanical follow, then rough inspections, then insulation and drywall. Cabinets, counters, tile, flooring, fixtures and paint follow in sequence, with final inspections at the end. Long-lead items like impact windows, doors and certain roofing materials should be ordered the week you close.

Ask for a written schedule with dates, and walk the job weekly. Photos from every visit create a record for draws, for the insurer and for any disagreement. During hurricane season, plan for weather days and keep the site secured, with a plan for covering open roof sections and protecting delivered materials when a storm is forecast.

When a contractor relationship goes wrong

Most contractor problems show up as small signals before they become big ones: missed start dates, crews that stop showing, requests for payment ahead of the schedule, or work that fails inspection repeatedly. Address them early and in writing. Refer to the contract, the scope and the schedule, and ask for a specific plan to get back on track.

If you need to part ways, do it by the contract. Document the work completed with photos, have it inspected, settle payment for completed work against lien releases, and get a new contractor to pull a permit change if required. Clean records and clean releases let a replacement contractor pick up the job without inheriting someone else’s problems.

Straight answers

Questions investors ask

How do I verify a Florida contractor license?

Search the license on the Florida Department of Business and Professional Regulation website by name or license number. Confirm it is active, that it covers the type of work you are hiring for, and that the business name matches the contract.

Can a handyman do work on my rehab?

For work that does not require a license or permit, such as painting or minor repairs, often yes. Electrical, plumbing, mechanical, roofing and structural work require licensed contractors and permits in Florida.

How much deposit should a contractor get?

Keep deposits modest and tied to a specific purpose, such as ordering long-lead materials. Pay the rest against completed milestones that match your draw schedule, with lien releases for each payment.

Does the lender need my contractor’s bid?

Yes, for rehab loans the contractor bid or scope of work is part of the document package. It shows what the rehab budget will pay for and becomes the basis for the draw schedule.

See the addresses. Walk the houses. Close with the money already lined up.

Buyer access is free. Tell us what you buy and where, and we will open the full listings: addresses, photos, access instructions and the financing terms behind each one.